Interest on delayed possession is prescribed, not negotiated. The rate is fixed by rule. The date it starts running depends on which remedy under Section 18 is claimed. Both must be established on the record.
The rate
Rule 17 of the Rajasthan Real Estate (Regulation and Development) Rules, 2017 prescribes the rate: the State Bank of India’s highest marginal cost of lending rate plus two per cent.
The same rate applies both ways. It is what the promoter owes on delay, and what an allottee owes on default in payment.
SBI revises its marginal cost of lending rate periodically. The applicable rate is the one in force over the period for which interest is claimed, not the rate on the date of filing.
What Section 18 provides
Section 18 · RERA Act, 2016 · Return of Amount and Compensation
(1) If the promoter fails to complete or is unable to give possession of an apartment, plot or building,—
(a) in accordance with the terms of the agreement for sale or, as the case may be, duly completed by the date specified therein; or
(b) due to discontinuance of his business as a developer on account of suspension or revocation of the registration under this Act or for any other reason,
he shall be liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of that apartment, plot, building, as the case may be, with interest at such rate as may be prescribed in this behalf including compensation in the manner as provided under this Act:
Provided that where an allottee does not intend to withdraw from the project, he shall be paid, by the promoter, interest for every month of delay, till the handing over of the possession, at such rate as may be prescribed.
Where interest starts
Remaining in the project. Interest runs from the possession date specified in the agreement for sale, for every month of delay, until possession is handed over. The proviso to Section 18(1) says so.
The date is the one in the agreement. It is not the date the promoter acknowledged the delay, and it is not the date of the complaint. Check whether a grace period is attached to the clause.
Withdrawing from the project. Interest runs from the date of each payment. In Kolkata West International City Pvt. Ltd. v. Devasis Rudra, Civil Appeal No. 3182 of 2019, decided on 25 March 2019 — an appeal from proceedings under the Consumer Protection Act — the Supreme Court ordered refund with interest running from the date of payment till realisation rather than from the date possession fell due. On a refund the promoter has held the money from the day it was paid.
Fortune Infrastructure v. Trevor D’Lima, (2018) 5 SCC 442, and Imperia Structures Ltd. v. Anil Patni, (2020) 10 SCC 783, proceed on the same restitutionary basis. In M/s Newtech Promoters and Developers Pvt. Ltd. v. State of U.P., (2022) 1 SCC 1, Civil Appeal Nos. 6745–6749 of 2021, decided on 11 November 2021, the Court held that the right of an allottee under Section 18(1) to refund with interest is unconditional and absolute.
The two start dates produce different figures on the same facts. Both should be worked out before the election is made.
Proving the figure
A claim for interest is a claim for a specific sum. The Authority adjudicates on what is claimed and proved.
Produce the clause fixing possession. Produce the payment schedule, with each date and amount. Produce the rate applied for each period, with its source. Produce the arithmetic.
A total advanced without its working invites an objection at the hearing, and the hearing is adjourned to meet it.
Where the claim is filed
Interest is claimed before the Authority under Section 31, in Form N, prescribed by rule 35(1) of the Rajasthan Rules, 2017, together with the claim for refund or possession. Confirm the prescribed fee on the portal at the time of filing.
Compensation is separate. It is claimed before the Adjudicating Officer under Sections 71 and 72, in Form O, prescribed by rule 36(1), and requires proof of the loss itself.
Common defects
Applying the current rate to the whole period instead of the rate in force over each part of it. Running interest from the date of complaint. Overlooking an extension of registration that bears on the start date. Filing without the payment history, the bank statements and the agreement in full.
An order awarding interest still has to be enforced, and how RERA Rajasthan orders are executed explains the recovery route.
This article sets out the general position under the Real Estate (Regulation and Development) Act, 2016 and the Rajasthan Real Estate (Regulation and Development) Rules, 2017. It is written for general information and is not legal advice on any specific matter.