Project Takeover Does Not Wipe Out Builder’s Liabilities, Holds Rajasthan RERA Appellate Tribunal

Nitesh Kumar
Author: Nitesh Kumar | Advocate, Rajasthan High Court

The learned Rajasthan Real Estate Appellate Tribunal, Jaipur, has upheld the order of the RERA Adjudicating Officer granting compensation to a homebuyer for delay in possession in a project in VKI area of Jaipur. The case highlights the continuing liability of a new promoter when a real estate project is transferred, reaffirming that obligations under the Real Estate (Regulation and Development) Act, 2016 (RERA Act) cannot be avoided by claiming subsequent takeover of a project.

Case Background

Complainant X booked a flat in a housing project, originally launched by Builder Y (erstwhile promoter), for a total price of Rs 23,50,000. An Agreement for Sale was executed on 31 December 2016 with possession promised by 31 December 2018. The complainant paid Rs 9,40,000. However, the project remained incomplete.

Later, the project was transferred to Developer Z after securing consent from two-thirds of the allottees. The new promoter registered the project afresh with Raj-RERA in 2020.

Due to the delay, the complainant first sought a refund before RERA. In March 2021, the Authority ordered a refund after deducting 10% as administrative charges. That refund was made, and an appeal filed by the promoter against the refund order was dismissed in November 2023.

Subsequently, Complainant X filed another complaint in 2024 seeking compensation for financial loss, interest paid on bank loan, mental agony, and litigation costs. The Adjudicating Officer allowed the claim and awarded:

  • Rs 5,00,000 as compensation for financial loss.
  • Rs 80,000 for deficiency in service and mental agony.
  • Rs 20,000 towards litigation cost.

The promoter appealed this order before the Appellate Tribunal.

Issues Raised

  1. Whether the subsequent promoter (Developer Z) could be held liable for compensation when the delay was caused by the erstwhile promoter.
  2. Whether the Adjudicating Officer erred in awarding compensation despite an earlier RERA order denying interest.
  3. Whether the refund already granted settled the matter completely, leaving no scope for further claims.

Legal Findings

The Tribunal examined Section 15(2) of the RERA Act, which provides that when a project is transferred to a new promoter with consent of two-thirds allottees, the incoming promoter must take on all obligations and liabilities of the previous promoter.

The Tribunal relied on the Supreme Court ruling in M/s Newtech Promoters and Developers Pvt. Ltd. v. State of U.P., (2022) 1 SCC 209, decided on 11 November 2021, which clarified that while RERA Authorities deal with refund and interest, the Adjudicating Officer has independent jurisdiction to award compensation under Sections 71 and 72 of the Act.

The Tribunal observed that:

  • The complainant had been deprived of timely possession and had to pay bank loan interest.
  • The complainant lost the opportunity to use or let the flat.
  • The complainant endured prolonged litigation and mental agony.

Accordingly, lump sum compensation awarded by the Adjudicating Officer was justified.

Relief Granted

The Tribunal dismissed the promoter’s appeal and affirmed the Adjudicating Officer’s order dated 5 September 2024. Developer Z must pay:

  • Rs 5,00,000 as compensation.
  • Rs 1,00,000 (Rs 80,000 + Rs 20,000) for deficiency in service, mental agony, and litigation cost.

In case of non-compliance within 45 days, simple interest at 6% p.a. will accrue on the awarded amount until payment.

Takeaways

This judgment reiterates that:

  • A new promoter who takes over a project inherits all liabilities of the previous promoter under Section 15 of the RERA Act.
  • Compensation for financial loss and mental agony can be claimed separately, even if refund orders earlier denied interest.
  • Homebuyers are entitled to relief not just for monetary loss but also for mental and physical distress caused by delay.

The ruling indicates that a project takeover carries full liability with it, and that the remedies under the Act extend beyond refund to compensation determined by the Adjudicating Officer.

Read the full judgement here

What the Act gives an allottee against a promoter, and the remedies that follow, are set out in this note on RERA Rajasthan.

This is a report of a decision of the Rajasthan Real Estate Appellate Tribunal, Jaipur, written for general information. Party names and identifying particulars have been omitted. It is not legal advice on any specific matter.

Leave a Reply

Your email address will not be published. Required fields are marked *

Disclaimer: This website has been designed only for the purposes of dissemination of basic information on practice areas of Prism Law Firm; information which is otherwise available on the internet, various public platforms and social media. Careful attention has been given to ensure that the information provided herein is accurate and up-to-date. However, Prism Law Firm is not responsible for any reliance that a reader places on such information and shall not be liable for any loss or damage caused due to any inaccuracy in or exclusion of any information, or its interpretation thereof. Reader is advised to confirm the veracity of the same from independent and expert sources.

This website is not an attempt to advertise or solicit clients, and does not seek to create or invite any lawyer-client relationship. The links provided on this website are to facilitate access to basic information on Prism Law Firm and different areas of law for information purposes, and, to share the various thought initiatives undertaken by it. The content herein or on such links should not be construed as a legal reference or legal advice. Readers are advised not to act on any information contained herein or on the links and should refer to legal counsels and experts in their respective jurisdictions for further information and to determine its impact.

Prism Law Firm advises against the use of the communication platform provided on this website for exchange of any confidential, business or politically sensitive information. User is requested to use his or her judgment and exchange of any such information shall be solely at the user’s risk.

Prism Law Firm uses cookies on its website to improve its usability. This helps us in providing a good user experience and to also help in improving our website. By continuing to use our website without changing your privacy settings, you agree to use our cookies links to which has been provided above.

This notice is shown once. By closing it, and on each later visit to this website, you confirm that you have read and accepted it, and that you are seeking information about Prism Law Firm of your own accord.