The learned Rajasthan Real Estate Appellate Tribunal, Jaipur, has upheld the order of the RERA Adjudicating Officer granting compensation to a homebuyer for delay in possession in a project in VKI area of Jaipur. The case highlights the continuing liability of a new promoter when a real estate project is transferred, reaffirming that obligations under the Real Estate (Regulation and Development) Act, 2016 (RERA Act) cannot be avoided by claiming subsequent takeover of a project.
Case Background
Complainant X booked a flat in a housing project, originally launched by Builder Y (erstwhile promoter), for a total price of Rs 23,50,000. An Agreement for Sale was executed on 31 December 2016 with possession promised by 31 December 2018. The complainant paid Rs 9,40,000. However, the project remained incomplete.
Later, the project was transferred to Developer Z after securing consent from two-thirds of the allottees. The new promoter registered the project afresh with Raj-RERA in 2020.
Due to the delay, the complainant first sought a refund before RERA. In March 2021, the Authority ordered a refund after deducting 10% as administrative charges. That refund was made, and an appeal filed by the promoter against the refund order was dismissed in November 2023.
Subsequently, Complainant X filed another complaint in 2024 seeking compensation for financial loss, interest paid on bank loan, mental agony, and litigation costs. The Adjudicating Officer allowed the claim and awarded:
- Rs 5,00,000 as compensation for financial loss.
- Rs 80,000 for deficiency in service and mental agony.
- Rs 20,000 towards litigation cost.
The promoter appealed this order before the Appellate Tribunal.
Issues Raised
- Whether the subsequent promoter (Developer Z) could be held liable for compensation when the delay was caused by the erstwhile promoter.
- Whether the Adjudicating Officer erred in awarding compensation despite an earlier RERA order denying interest.
- Whether the refund already granted settled the matter completely, leaving no scope for further claims.
Legal Findings
The Tribunal examined Section 15(2) of the RERA Act, which provides that when a project is transferred to a new promoter with consent of two-thirds allottees, the incoming promoter must take on all obligations and liabilities of the previous promoter.
The Tribunal relied on the Supreme Court ruling in M/s Newtech Promoters and Developers Pvt. Ltd. v. State of U.P., (2022) 1 SCC 209, decided on 11 November 2021, which clarified that while RERA Authorities deal with refund and interest, the Adjudicating Officer has independent jurisdiction to award compensation under Sections 71 and 72 of the Act.
The Tribunal observed that:
- The complainant had been deprived of timely possession and had to pay bank loan interest.
- The complainant lost the opportunity to use or let the flat.
- The complainant endured prolonged litigation and mental agony.
Accordingly, lump sum compensation awarded by the Adjudicating Officer was justified.
Relief Granted
The Tribunal dismissed the promoter’s appeal and affirmed the Adjudicating Officer’s order dated 5 September 2024. Developer Z must pay:
- Rs 5,00,000 as compensation.
- Rs 1,00,000 (Rs 80,000 + Rs 20,000) for deficiency in service, mental agony, and litigation cost.
In case of non-compliance within 45 days, simple interest at 6% p.a. will accrue on the awarded amount until payment.
Takeaways
This judgment reiterates that:
- A new promoter who takes over a project inherits all liabilities of the previous promoter under Section 15 of the RERA Act.
- Compensation for financial loss and mental agony can be claimed separately, even if refund orders earlier denied interest.
- Homebuyers are entitled to relief not just for monetary loss but also for mental and physical distress caused by delay.
The ruling indicates that a project takeover carries full liability with it, and that the remedies under the Act extend beyond refund to compensation determined by the Adjudicating Officer.
What the Act gives an allottee against a promoter, and the remedies that follow, are set out in this note on RERA Rajasthan.
This is a report of a decision of the Rajasthan Real Estate Appellate Tribunal, Jaipur, written for general information. Party names and identifying particulars have been omitted. It is not legal advice on any specific matter.